Project Details
CLIENT: | ABP |
LOCATION: | Southampton |
START DATE: | |
COMPLETION DATE: | |
VALUE: | £500,000 |
Rank Hovis Carpark Dock Gate 10 Southampton Docks
– Removal of existing concrete structures
– Removal and replacement of Security fencing
– Installation of combined kerb drainage, manholes, catch pits, Gattic slot drains and by-pass interceptor
– Installation of cable ducting and associated draw pits
– Removal and disposal of contaminated soil
– Formation of new vehicle parking area and footways
– New Surfacing to parking area and footways
– Line marking
– Installation of new Lighting system inclusive of LED Lamps
– Reinforced concrete retaining structures.
– Duration of 9 weeks
Contact PTC Today
If you’d like to talk to us about a project, or anything else, we’d love to hear from you.