Project Description
Stage 1– Flood risk prevention works
Construction of two new flood defence bund walls for transformers C1MT and C2MT
Modification of the Switch room to protect the installed equipment from flooding by installing two new flood doors, sealing cable trenches, and relocating wall mounted air vents.
Stage 2- Temporary switch board works
Construction of a new concrete foundation for temporary Switchroom and board.
Civil works to prepare the ground and foundation for the temporary board including the modification, installation, and reinstatement of fencing around the temporary board location.
Stage 3 – Main Switch room works
Foundation works for main Switch room.
Construct new steel framed Switch room.
Petersfield Substation
Client
SSEN
Location
Petersfield
Completion Date
Jan 2022
Value
£919,000